November 15-19, 2010 1) Coal Ave. from Sycamore to Ash: Crews will remove asphalt.
2) University Blvd. SE from north of Basehart Road to between Coal Place and Lead Avenue:
Construction will continue and traffic will be restricted.
3) Coal Ave. from Mulberry to Sycamore: Crews will begin laying storm drainage lines and inserting sleeves
in those lines.
4) Coal SE & University SE: Crews will begin laying storm drainage trunk lines and lateral lines.
November 22-24, 2010 (Thanksgiving Week – Shorter Schedule due to Holiday) 1) Coal Ave. from Ash to University: Crews will remove asphalt.
2) University Blvd. SE from north of Basehart Road to between Coal Place and Lead Avenue:
Construction will continue and traffic will be restricted.
3) Coal SE & University SE: Crews will continue laying storm drainage trunk lines and lateral lines.
4) Coal Ave. from Mulberry to Sycamore: Crews will begin relocating water meters & other crews will
prepare the roadway for repaving.
November 29-December 3, 2010 1) Coal Ave. from Ash to University & from University to Buena Vista: Crews will remove asphalt.
2) Coal from Mulberry to Sycamore: Crews will continue relocating water meters and preparing the roadway
for repaving. Once preparation is complete, crews will begin installing base course (the material under the
asphalt).
General Information:
Construction is expected to last approximately 18 months, through spring 2012. The contractor will work in approximate 5-block areas, finishing all construction in one area before moving on to the next. 2 crews will be working on the project at the same time. Initial work zones will be at Coal & I-25, heading east and at Coal & University, heading east. Regular work hours will be daylight hours (7 a.m.-5 p.m. Monday-Friday) although crews may work later hours or on weekends if needed due to an emergency or unforeseen circumstance.
|